CAPM Exam Prep 41, Determine Budget — Baselines and Reserves

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams. In this episode you will learn: - The cost baseline is a time-phased budget that includes activity cost estimates plus contingency reserves. - Contingency reserves are for identified risks, or "known-unknowns," and are controlled by the Project Manager. - Management reserves are for unidentified risks, or "unknown-unknowns," and are controlled by senior management, not the PM. - A critical exam trap is knowing that management reserves are NOT part of the cost baseline but are part of the total project budget. - The total project budget is calculated by adding the management reserve to the cost baseline. For more free exam prep tools, practice questions, and AI-powered explanations, visit https://open-exam-prep.com/ or YouTube Channel: https://www.youtube.com/@Open-exam-prep

0:00-3:31

transcript

No transcript — this publisher did not publish one.

show notes

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams.

In this episode you will learn:
- The cost baseline is a time-phased budget that includes activity cost estimates plus contingency reserves.
- Contingency reserves are for identified risks, or "known-unknowns," and are controlled by the Project Manager.
- Management reserves are for unidentified risks, or "unknown-unknowns," and are controlled by senior management, not the PM.
- A critical exam trap is knowing that management reserves are NOT part of the cost baseline but are part of the total project budget.
- The total project budget is calculated by adding the management reserve to the cost baseline.