CAPM Exam Prep 37, Schedule Compression — Crashing vs Fast-Tracking
transcript
show notes
This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams.
In this episode you will learn:
- Crashing a schedule involves adding resources to critical path activities and always increases project costs.
- Fast-tracking a schedule involves performing sequential tasks in parallel and always increases project risk and the potential for rework.
- Both crashing and fast-tracking are only effective when applied to activities on the critical path.
- A common exam trap is a scenario suggesting the compression of a non-critical activity, which does not shorten the overall project duration.
- Resource leveling is a resource optimization technique that often lengthens the schedule and should not be confused with schedule compression.