CAPM Exam Prep 37, Schedule Compression — Crashing vs Fast-Tracking

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams. In this episode you will learn: - Crashing a schedule involves adding resources to critical path activities and always increases project costs. - Fast-tracking a schedule involves performing sequential tasks in parallel and always increases project risk and the potential for rework. - Both crashing and fast-tracking are only effective when applied to activities on the critical path. - A common exam trap is a scenario suggesting the compression of a non-critical activity, which does not shorten the overall project duration. - Resource leveling is a resource optimization technique that often lengthens the schedule and should not be confused with schedule compression. For more free exam prep tools, practice questions, and AI-powered explanations, visit https://open-exam-prep.com/ or YouTube Channel: https://www.youtube.com/@Open-exam-prep

0:00-3:12

transcript

No transcript — this publisher did not publish one.

show notes

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams.

In this episode you will learn:
- Crashing a schedule involves adding resources to critical path activities and always increases project costs.
- Fast-tracking a schedule involves performing sequential tasks in parallel and always increases project risk and the potential for rework.
- Both crashing and fast-tracking are only effective when applied to activities on the critical path.
- A common exam trap is a scenario suggesting the compression of a non-critical activity, which does not shorten the overall project duration.
- Resource leveling is a resource optimization technique that often lengthens the schedule and should not be confused with schedule compression.