CAPM Exam Prep 36, Critical Path Method — Longest Path and Float

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams. In this episode you will learn: - The critical path is the longest duration path through the network, determining the shortest possible project timeline. - Activities on the critical path have zero total float; any delay to these tasks directly delays the project's end date. - Total float is the delay an activity can have without impacting the project finish date, while free float is the delay possible without affecting the next successor's start. - Exam questions often try to trick you by confusing the longest path (duration) with the path containing the most activities. - Near-critical paths are high-risk and must be monitored closely, as minor delays can make them become the new critical path. For more free exam prep tools, practice questions, and AI-powered explanations, visit https://open-exam-prep.com/ or YouTube Channel: https://www.youtube.com/@Open-exam-prep

0:00-3:01

transcript

No transcript — this publisher did not publish one.

show notes

This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams.

In this episode you will learn:
- The critical path is the longest duration path through the network, determining the shortest possible project timeline.
- Activities on the critical path have zero total float; any delay to these tasks directly delays the project's end date.
- Total float is the delay an activity can have without impacting the project finish date, while free float is the delay possible without affecting the next successor's start.
- Exam questions often try to trick you by confusing the longest path (duration) with the path containing the most activities.
- Near-critical paths are high-risk and must be monitored closely, as minor delays can make them become the new critical path.