CAPM Exam Prep 34, Sequence Activities — Dependencies and PDM
transcript
show notes
This podcast is made by Ran Chen, who holds an EA license, Insurance and Securities licenses (Series 6, 63, 65), and the CFP® designation. He is passionate about opening access to high-quality exam preparation resources and helping learners prepare more effectively for professional certification exams.
In this episode you will learn:
- The Precedence Diagramming Method (PDM) uses four dependency types: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and the rarely used Start-to-Finish (SF).
- Finish-to-Start (FS) is the most common and default logical relationship on the CAPM exam.
- Dependencies are categorized into four attributes: Mandatory (hard logic), Discretionary (soft logic), External (outside project control), and Internal (within project control).
- A key exam trap is distinguishing between inflexible mandatory dependencies and flexible discretionary dependencies, which can be altered to compress the schedule.
- The Start-to-Finish (SF) dependency is counter-intuitive and almost always an incorrect answer choice on the exam due to its rarity.